The Challenge:

Cube designed, manufactured, tested, coated & delivered a DNV 2.7-3 R30 SXX MGW=8000kg rated subsea basket to client specifications in 6 weeks over the over the Christmas / NY break.

The Solution:

In order to manage the tight schedule, Cube locked down all client specifications early, committed to early steel procurement in parallel with the design process then issued fabrication drawings, cutting lists & .dxf files directly to our fabricator.  Close communication and scheduling over the Christmas / NY break allowed all workfronts to progress in accordance with the plan.

The Scope:

Deliver a subsea basket in accordance with the strength, fabrication & testing requirements of DNV 2.7-3 R30 SXX MGW=8000kg as follows:

  • Concept development
  • Comply with client specifications & functional requirements
  • Engineering design in accordance with the strength requirements of DNV 2.7-3 R30 SXX
  • Manufacture & test in accordance with the material & testing requirements of DNV 2.7-3 R30 SXX
  • Integrate design & manufacture processes
  • Expedite a quick turn around for load testing & coating