FSO Liberdade Decommissioning Verification

The Challenge

The FSO Liberdade decommissioning campaign required the STLB to be jacked-up, released and subsequently recovered using an offshore crane. Santos required independent assurance that the lifting load path, design loads and contractor assumptions complied with the project design basis, lifting standard and marine-operation requirements.  Two lifts were considered, a) Jacking the STLB up prior to freefall release and b) future retrieval through the splash zone and in-air lift by offshore crane vessel.  The challenge was in the buoys unknown ballast integrity and subsequent lift weight risk.

The Solution

We independently reviewed the STLB release load path from the buoy through the temporary lifting equipment into the FSO hull and then the subsequent recovery lift through the splash zone and onto deck by a crane vessel.   We checked load cases, FEA assumptions, component utilisations, strain criteria and design changes, then documented the findings in the STLB Lift Verification Report and supported HAZID and technical close-out.

The Scope

  • Basis of Design, release methodology and structural analysis review
  • Complete load-path, load-case and FEA consistency assessment
  • Code-compliance review of lifting equipment, temporary works and FSO structure
  • Lift Verification Report, HAZID support and technical close-out

The Outcome

Cube Offshore delivered a documented assessment of the STLB jacking system and recovery lift, confirming code compliance across the identified load path and recording the governing utilisations, strain limits and design changes.  Critical components were verified including a strain based assessment of the bolt on single point lift padeye with a design rating of 1419 t.

 

Credit given to Pyseas for the original design and Cyan for offshore planning & operations.